Mühleberg Nuclear Power Plant
Annual revision of Mühleberg nuclear power plant completed

Bern (ots)

The Swiss supervisory authority ENSI (Federal Nuclear Safety Inspectorate) has authorised the repowering of Mühleberg nuclear power plant (KKM). The facility had been closed since 10 August 2014 for the annual maintenance work. During this time staff replaced fuel elements and carried out maintenance work as well as upgrades.

All the work was performed successfully, meeting all safety targets. 36 of the 240 fuel elements were replaced and extensive preventive work was carried out on components, fittings and systems. An inspection of the core shroud revealed short vertical cracks along a horizontal weld. A technical assessment showed that these had no effect on the plant's successful repowering and the operational safety. The KKM has informed the Federal Nuclear Safety Inspectorate (ENSI) of this finding. The core shroud inspection programme will be continued in the course of the 2015 annual revision, when ultrasonic testing will be carried out.

During the last operating cycle the KKM generated a gross volume of 3112 GWh - the third-largest electricity output since 1972.

For more information on the core shroud, visit: http://bkw.ch/kernmantel.html (in German and French)

Contact:

Murielle Clerc
media@bkw.ch
058 477 51 07

Plus de actualités: BKW Energie AG
Plus de actualités: BKW Energie AG
  • 28.08.2014 – 07:00

    Group Strategy / BKW sells interest in Jungfraubahn Holding AG

    Bern (ots) - BKW is selling its interest in Jungfraubahn Holding AG to several investors. The planned transaction will extend BKW's financial scope and accelerate the drive to build up new business fields. This supports BKW's new business focus as a provider of comprehensive energy and infrastructure services. The transaction involving the sale of BKW's stake to ...

  • 20.08.2014 – 07:00

    BKW Distribution Grid / ElCom recognises higher value for distribution grid

    Bern (ots) - The Federal Electricity Commission (ElCom) has recognised a higher value for the distribution grid and has adjusted the figure upwards by around CHF 400 million. Based on this decision, BKW is able to claim higher income for the use of the distribution grid. BKW welcomes this decision, which will enable additional investments in an innovative and ...

  • 18.08.2014 – 07:00

    BKW Pricing / Slight increase in electricity prices for 2015

    Bern (ots) - Electricity prices will increase slightly for BKW's customers in 2015. This adjustment is mainly due to a significant increase in the statutory charges introduced to promote renewable energies (CRF). Private and basic-provision commercial customers will pay an average of 2.9% more for their electricity in 2015, primarily due to the higher statutory fees. This percentage may vary between individual customers, ...