Richmont Mines

Richmont Reports Third Quarter Operational Results; Island Gold Completes a 25-Day Electrical Mill Upgrade and Remains On-Track to Meet, or Exceed, Revised Guidance

Toronto (ots/PRNewswire)

Richmont Mines Inc. (TSX: RIC) (NYSE MKT: RIC) ("Richmont" or the "Corporation"), reports that the Island Gold Mine delivered another in-line quarter of operational results and remains on track to meet, or exceed, its positively revised annual guidance. During the quarter, a successful mine and mill electrical upgrade was completed as planned at the Island Gold Mine, which would support potential future production growth opportunities that are currently under review as part of the 2016 Preliminary Economic Assessment ("PEA") update. Overall, the Corporation remains on target to achieve company-wide revised guidance. (All amounts are in Canadian dollars unless otherwise indicated).

HIGHLIGHTS FOR THE THIRD QUARTER

- The Island Gold Mine produced 14,031 ounces of gold (13,673 ounces 
  sold), in-line with plan, as lower production was forecasted for 
  the quarter due to required downtime related to the scheduled mine 
  and mill electrical upgrade. The Island Gold Mine remains on track 
  to meet, or exceed, revised production guidance for the year.
- Company-wide production was 18,856 ounces of gold (17,774 ounces 
  sold) for the quarter, which positions the Corporation to achieve 
  revised company-wide production guidance for the year.
- Cash costs[1] for the Island Gold Mine were $958 per ounce (US$734 
  per ounce), in-line with plan, as lower production was anticipated 
  for the quarter due to the 25-day mill shutdown to complete the 
  electrical upgrade. Cash costs for the Island Gold Mine remain on 
  track to meet, or exceed, revised guidance for the year.
- Company-wide cash costs for the quarter were $1,063 per ounce 
  (US$815 per ounce), in-line with revised guidance.
- Revenues for the quarter were $31.2 million (US$23.9 million), at 
  an average realized gold price of $1,754 per ounce (US$1,344 per 
  ounce).
- Richmont ended the quarter with a reduced cash balance of $78.9 
  million (US$60.1 million), in-line with plan due to lower 
  production and higher cash costs related to the 25-day mill 
  shutdown as well as higher capital investment requirements as 
  anticipated for the quarter.
- On September 12, 2016, the Corporation announced positive revisions
  to its 2016 operational guidance driven by significantly better 
  than expected performance from the Island Gold Mine in the first 
  six months of the year.

"The third quarter was a pivotal quarter for the Island Gold Mine as a strategic electrical upgrade was successfully completed, which now positions this core asset for potential future production growth and improved reliability. Following the upgrade, mill and underground mine productivities have returned to target levels and we expect to deliver improved performance and higher grades during the fourth quarter as we begin to develop in ore in the higher-grade third mining horizon." stated Renaud Adams, CEO. He continued, "At the Beaufor Mine, after a difficult transition to the Q Zone, we expect to deliver higher production and lower costs during the fourth quarter as we increase the proportion of stope mining in the higher grade Q Zone and process the 6,000 tonnes of broken ore that remained in inventory at the end of the quarter."

___________________________

[1] Refer to the Non-IFRS Performance Measures disclosure presented at the end of this press release.

THIRD QUARTER OPERATIONAL HIGHLIGHTS

Third quarter operational highlights for the Island Gold and Beaufor mines are provided in the tables below:

Production Highlights




9-Months  2016 Revised   
Q2 15  Q3 15  Q4 15     Q1 16   Q2 16  Q3 2016    
2016      Guidance
Gold Produced
(oz)
Island Gold
Mine          14,997 15,076 14,203[1] 26,589  18,617   14,031[3] 
59,237 75,000-80,000     
Beaufor
Mine           7,082  5,714  5,652     4,615   4,703    4,825    
14,143


23,000-26,000[4]
Monique Mine   4,235  2,688  2,525     1,165[2]    -        -    
1,165   
Total
Produced (oz) 26,314 23,478 22,380    32,369  23,320   18,856   
74,545 98,000-106,000


[1] Q4 2015 production includes a 3 week underground mine 
shutdown.
[2] Processing of the remaining stockpile pad at the depleted 
Monique Mine
was completed at the end of January 2016.
[3] Q3 2016 production includes a 16-day underground mine 
shutdown and a
25-day mill shutdown.
[4] Guidance includes production from the Beaufor and Monique 
mines.

Cash Cost Highlights



9-Months    2016 Revised
Q2 15  Q3 15   Q4 15  Q1 16   Q2 16   Q3 16    
2016        Guidance
Cash Costs
($)[1]
Island Gold
Mine            $954   $890  $1,026   $674    $766    $958     
$770       $800-$840
Beaufor Mine  $1,062   $974  $1,084 $1,398  $1,486  $1,411   
$1,433

$1,150-$1,300[3]
Monique Mine    $914 $1,005    $977 $1,185       -       -   
$1,185
Total Cash
Costs ($)[1]    $974   $926  $1,034   $806    $903  $1,063     
$899       $885-$945
Cash Costs
(US$)[(1)(2)]
Island Gold
Mine            $776   $680    $768   $491    $595    $734     
$583       $610-$640
Beaufor Mine    $864   $744    $812 $1,018  $1,154  $1,082   
$1,084

$875-$1,000
Monique Mine    $743   $768    $731   $863       -       -     
$897
Total Cash
Costs (US$)[1]  $792   $707    $774   $587    $701    $815     
$680       $675-$720


[1] Refer to the Non-IFRS Performance Measures disclosure 
presented at the
end of this press release.
[2] The revised guidance assumes an exchange rate of 1.33 for 
January to
June and 1.30 for July to December.
[3] Guidance includes cash costs from the Beaufor and Monique 
mines.

Operational Highlights




Q2 15   Q3 15     Q4 15  Q1 16   Q2 16  Q3
16
Island Gold Mine
Underground tpd         759      669    657[1]    853     911    
735[2]
Mill tpd                787      722    656[1]    834     878    
640[2]
Mill head grade (g/t)  6.73     7.27   7.62     11.31    7.51   
7.70
Recoveries (%)         96.8     97.1   96.0      96.3    96.5   
96.4
Beaufor Mine
Underground tpd         360      338      306     323     286    
282
Mill head grade (g/t)  6.05     5.93     6.30    4.96    5.27   
5.62
Recoveries (%)         98.6     98.6     98.4    98.7    98.1   
97.3


[1]Q4 2015 underground productivity includes a 3 week mine 
shutdown
and a 2 week mill shutdown.

[2]Q3 2016 productivity includes a 16-day underground mine 
shutdown
and a 25-day mill shutdown.

Island Gold Third Quarter Highlights

- Production for the quarter was 14,031 ounces of gold (13,673 ounces
  sold), in-line with plan, which forecasted lower production as part
  of the planned electrical upgrade. The operation remains on track 
  to meet, or exceed, revised production guidance.
- Cash costs for the quarter were $958 per ounce (US$734 per ounce), 
  in-line with higher costs that were anticipated for the quarter due
  to the lower production estimated for the quarter. Cash costs 
  remain on track to meet, or exceed, revised guidance.
- A mine and mill electrical upgrade was successfully completed as 
  planned during the quarter. The upgrade included a 25-day mill 
  shutdown, which has been incorporated into the revised guidance. 
  The mine and mill upgrade would support the potential production 
  growth scenarios that are currently under review as part of the 
  2016 PEA update.
- During the quarter, the mine reported higher than the planned mill 
  head grade of 7.70 g/t gold, resulting from stope mining activities
  in the first mining horizon and development in ore in the lower 
  grade extensions of the second mining horizon. During the fourth 
  quarter, it is expected that stope mining will begin in the eastern
  and western extensions of the second mining horizon and development
  in ore will begin in the 760 and 780 metre levels, located in the 
  third mining horizon.
- During the quarter, underground mine productivity averaged 735 
  tonnes per day, including 16 days of downtime related to the 
  electrical upgrade, or 890 tonnes per day excluding the downtime.
- Mill productivity averaged 640 tonnes per day for the quarter, 
  including 25 days of downtime related to the electrical upgrade, or
  878 tonnes per day excluding the downtime.
- The development of the main ramp continued and reached a vertical 
  depth of 810 metres at the end of the quarter. It is expected that 
  the ramp development will reach the bottom of the higher grade 
  third mining horizon at the 860 metre level in the first quarter of
  2017.
- Delineation drilling to date in the expanded 2016 PEA area 
  demonstrates the potential to grow our near-mine reserve inventory 
  and identify new resource blocks located within the 2016 PEA area. 
  These ounces could extend mine life above the 1,000 metre level and
  be incorporated into the near-term mine plan utilizing current 
  infrastructure. Initial results from the recently launched 18 to 24
  month Phase 2 exploration program continue to show the potential to
  increase resources laterally along strike, primarily to the east, 
  and at depth below the 1,000 metre level.

Beaufor Third Quarter Highlights

- Production for the quarter increased slightly over the prior 
  quarter to 4,825 ounces of gold (4,101 ounces sold) at an average 
  grade of 5.62 g/t. Production in the quarter was impacted by low 
  availability of underground mobile equipment, which resulted in 
  approximately 6,000 tonnes of broken ore at 7.0 g/t gold remaining 
  in inventory and unavailable for processing. It is expected that 
  this broken ore will be processed in the fourth quarter.
- As a result of the low availability of mobile equipment during the 
  quarter, the operation prioritized its efforts on waste development
  to better position stope mining operations in the higher grade Q 
  Zone in the fourth quarter.
- Cash costs for the quarter were $1,411 per ounce (US$1,082 per 
  ounce), consistent with the prior quarter.
- Grades and underground productivity are expected to increase in the
  fourth quarter as a greater proportion of stope mining is planned 
  from the higher grade Q Zone, which should contribute to higher 
  production and lower costs.

Upcoming News

- 2016 Preliminary Economic Assessment Update (late October 2016)
- Q3 2016 Financial Results and Conference Call (November 10, 2016)

Non-International Financial Reporting Standards ("IFRS") Performance Measures

In this press release, the term "cash costs per ounce" is used, which is a non-IFRS performance measure, and may not be comparable to similar measures presented by other companies. The Corporation believes that, in addition to conventional measures prepared in accordance with IFRS, the Corporation and certain investors use this information to evaluate the Corporation's performance. Accordingly, it is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. "Cash costs per ounce" is a common performance measure in the gold mining industry, but does not have any standardized definition. The Corporation reports cash cost per ounce based on ounces sold. Cash costs include mine site operating costs, administration and royalties but are exclusive of depreciation, accretion expense, capital expenditures and exploration and project evaluation costs.

About Richmont Mines Inc.

Richmont Mines has produced over 1.6 million ounces of gold from its operations in Quebec, Ontario and Newfoundland since beginning production. The Corporation currently produces gold from the Island Gold Mine in Ontario, and the Beaufor Mine in Quebec. The Corporation is also advancing development of the significant high-grade resource extension at depth of the Island Gold Mine in Ontario. With 35 years of experience in gold production, exploration and development, and prudent financial management, the Corporation is well-positioned to cost-effectively build its Canadian reserve base and to successfully enter its next phase of growth.

Forward-Looking Statements

This news release contains forward-looking statements that include risks and uncertainties. When used in this news release, the words "estimate", "project", "anticipate", "expect", "intend", "believe", "hope", "may", "objective" and similar expressions, as well as "will", "shall" and other indications of future tense, are intended to identify forward-looking statements. The forward-looking statements are based on current expectations and apply only as of the date on which they were made. Except as may be required by law or regulation, the Corporation undertakes no obligation and disclaims any responsibility to publicly update or revise any forward-looking statements or information, whether as a result of new information, future events or otherwise.

The factors that could cause actual results to differ materially from those indicated in such forward-looking statements include, without limitation, changes in the prevailing price of gold, the Canadian-United States exchange rate, grade of ore mined and unforeseen difficulties in mining operations and mine development that could affect revenue and production costs and future production. Other factors such as uncertainties regarding government regulations could also affect the results. Other risks are set out in Richmont's Annual Information Form, Annual Reports and periodic reports. The forward-looking information contained herein is made as of the date of this news release.

Cautionary note to US investors concerning resource estimates

Information in this press release is intended to comply with the requirements of the Toronto Stock Exchange and applicable Canadian securities legislation, which differ in certain respects with the rules and regulations promulgated under the United States Securities Exchange Act of 1934, as amended ("Exchange Act"), as promulgated by the SEC. The requirements of National Instrument 43-101 âEUR" Standards of Disclosure for Mineral Projects ("NI 43-101") adopted by the Canadian Securities Administrators differ significantly from the requirements of the United States Securities and Exchange Commission (the "SEC").

U.S. Investors are urged to consider the disclosure in our annual report on Form 20-F, File No. 001-14598, as filed with the SEC under the Exchange Act, which may be obtained from us (without cost) or from the SEC's web site: http://sec.gov/edgar.shtml.

National Instrument 43-101

The geological data in this news release has been reviewed by Mr. Daniel Adam, Geo., Ph.D., Vice-President, Exploration, an employee of Richmont Mines Inc., and a qualified person as defined by NI 43-101.

Mediacontact: Renaud Adams, President and CEO, Phone: +1-416-368-0291 ext. 101; Anne Day, Vice-President, Investor Relations, Phone: +1-416-368-0291 ext. 105

Weitere Storys: Richmont Mines
Weitere Storys: Richmont Mines
  • 12.09.2016 – 12:31

    Richmont Mines Announces Positive Revisions to 2016 Guidance

    Toronto (ots/PRNewswire) - Potential Production Increase at Island Gold of up to 45% over 2015 Richmont Mines Inc. (TSX: RIC) (NYSE MKT: RIC) ("Richmont" or the "Corporation") announces a positive revision to its 2016 operational guidance estimates driven by significantly better than expected performance from the Island Gold Mine. (All amounts are in Canadian dollars, unless otherwise indicated). - Company-wide annual ...